1.Original copy of basic information for project filing
1. Time
Working days: 09:00-17:00
2. Mode and Location
On-site processing:
Beijing Yanqing District Administrative Service Center: Comprehensive Service Desk for Engineering Construction Approval, 4F, No.60, Qingyuan Street, Yanqing District, Beijing
For online processing, please access: banshi.beijing.gov.cn
3. Process
(1) Application acceptance: Immediate
(2) Review and decision-making: Half a working day
(3) Issuance and delivery: Immediate
4. Fees
Free of charge
5. Authority in charge
Yanqing District Commission of Development and Reform
All information contained in materials submitted through the system must be accurate and valid.