Circular of Beijing Municipal Commission of Development and Reform and Beijing Municipal Bureau of Economy and Information Technology onFiling Management Work of Simple and Low-risk Construction Projects with Social Investment

Jing Fa Gai [2019] No.1647

To relevant entities,

To promote the implementation of Some Provisions on Optimizing the Examination and Approval Service for New Simple and Low Risk Construction Projects with Social Investment and Opinions on Improving the Examination and Approval Services for Simple and Low-risk Construction Projects, the related filing management work of simple and low-risk projects are hereby notified as follows:

I. Define the scope of filing

Simple and low-risk projects shall meet the building nature, purpose limitations, floor area, location and other requirements specified in the project list. The fixed assets investment projects among simple and low-risk projects such as new projects with social investment as well as renovated and expanded projects shall be recorded and assigned with the code.

The filing of foreign investment projects shall be subject to relevant measures for the administration of foreign investment projects of the state and Beijing.

II. Adjust the approval authority

For office, commercial, residential and other projects that fall within the scope of the Investment Project Catalogue Approved by the People's Government of Beijing Municipality (2018 edition), the confirmation will be cancelled and changed into filing. The development and reform commissions of various districts shall do a good job in project filing in accordance with relevant regulations.

III. Specify the division of functions

(i) The economy and information department is responsible for the filing of industry and informatization fixed-asset investment projects, while the development and reform department is responsible for the filing of other fixed-asset investment projects.

(ii) The economy and information department is responsible for the filing of industrial R&D projects on industrial land that meet the requirements of industrial policies and land use plans, while the development and reform department is responsible for the filing of R&D projects on other industrial land.

(iii) The development and reform department is responsible for the filing of the projects on industrial land whose industrial structure is adjusted into cultural innovation, commercial office and so on according to the law.

(iv) The economy and information department is responsible for the filing of supporting buildings indispensable for industrial projects.

IV. Reduce the handling time

As per the requirement of the Notice of National Development and Reform Commission on Embracing the Filing Management Work of World Bank Doing Business Assessment Standardization Projects, the filing work shallbe completed within 0.5 working days. Specifically, the filing authority shall complete the project code assignment within 0.5 working days from the date of receiving materials. The paper filing certificate is a post-filing service item. For projects that need the filing certificate, the filing authority shall provide corresponding services according to the needs of enterprises.

All entities shall strictly approve the projects, undertake the responsibilities of project filing management in accordance with laws and regulations, and do a good job in filing management. In case of special circumstances during the implementation process, they shall be reported to Beijing Municipal Commission of Development and Reform and Beijing Municipal Bureau of Economy and Information Technology in a timely manner.

Beijing Municipal Commission of Development and Reform and Beijing Municipal Bureau of Economy and Information Technology

December 2, 2019