Basic Documents.jpg

1. An original copy of "Application Form for Processing of Construction Projects" (Municipal Transportation Infrastructure Project - Engineering Construction Permit Phase) (Table J-2)

2. An original"Authorization letter for the Legal Representative of Construction Projects", and an original ID card of the authorized agent (for verification only)and a photocopy of it.(In the case of applying at the service window, the original will be verified on the spot, and the photocopy will be reserved; in the case of applying online, a scanned copy of both sides of the ID card shall be provided.)

3. Design drawings:

(1) Two sets of the original linear engineering drawings issued by a qualified design organization

Design drawings should meet the depth requirements regarding the preparation of preliminary design documents contained within the "Depth Regulations of Design Documents for Municipal Public Works" (2013 edition). It may be used for reference for electric power and telecommunications to meet relevant industrial standards. Terminal (plant) projects should also meet the specifications of the "Guideline for Handling Technical Documents for Planning and Design of Construction Projects" (Shi Gui Hua Guo Tu Fa [2018] No.87).

(2) One set of the original terminal (plant) projects engineering drawings issued by a qualified design organization, attached with the original corresponding site plan

Design drawings should meet the depth requirements regarding the preparation of preliminary design documents contained within the "Depth Regulations of Design Documents for Municipal Public Works" (2013 edition). It may be used for reference for electric power and telecommunications to meet relevant industrial standards. Terminal (plant) projects should also meet the specifications of the "Guideline for Handling Technical Documents for Planning and Design of Construction Projects" (Shi Gui Hua Guo Tu Fa [2018] No.87).

4. Major urban and rural infrastructure projects:

(1) In the case of applying for a project planning permit for the first time, an original approved preliminary design plan for expansion is required.

(2) For construction projects approved or examined and approved by the State Council or national ministries (commissions), an original approval or examination and approval document is required.

(3In the case of the preliminary design approved by the national ministries (commissions), an original approval document for preliminary design plan is required; in the case of applying for the construction project planning permit for the first time, an original approved preliminary design plan is required.

5. For government investment projects, an original document and a photocopy of the feasibility study approval or project approval document issued by the investment authority are required.

6. In the case of small-scale municipal projects, an original consulting schemes proposed by the corresponding professional companies shall be submitted.

Process, Time, Mode, Location, and Fees.png

1.  Office Hours,Method and Location

Weekdays: 9:00–12:00, 13:30–17:00

Extended service hours: 9:00–13:00 on Saturday (reservation required, except statutory holidays)

Beijing Municipality Government Affairs Service Center: Service Desk for Comprehensive Affairs, No.1, West Third Ring South Road, Fengtai District, Beijing (southwest corner of Liuliqiao).

Application for confidential and top-secret works of classified projects shall be submitted to: Beijing Municipal Administrative Center Government Affairs Service Center, Comprehensive Affairs Service Desk, (southeast corner of) No.48 Xinhua East Street, Tongzhou District, Beijing.

Weekdays: 9:00–11:30, 13:00-17:00

On-site processing: Government Service Hall, 1F, Block D, Yufa Airport Entrepreneurship Development Center, No. 12 Yushun Road, Yufa Town, Daxing District, Beijing  

2. Process

(1) Application acceptance: 2 working days for acceptance

(2) Review and decision: 4 working days for decision

(3) Issuance and delivery: Immediate production and issuance of certificate

3. Authority in charge

Beijing Municipal Commission of Planning and Natural Resources

Beijing Daxing International Airport Economic Zone (Daxing) Administrative Committee

Notes.jpg

Small municipal projects* can directly apply for construction project planning permits with the corresponding professional company consulting plan. For municipal transportation infrastructure projects other than small-scale municipal projects, the construction unit can be provided with multi-plan integration platform pre-communication and pre-coordination consulting services before it apply for the project planning permit.

Note: *The scope of application of small-scale municipal projects (excluding the “three zeros”(zero visits, zero approval, and zero investment) service scope of simple and low-risk projects under social investment): (I) Electricity: applicable to low-voltage power user access projects that apply for new electric power installations, capacity expansion, and other business expansion services for social investment construction projects in the city. Its voltage level shall be below 10KV (excluding 10KV); the installation capacity shall be within 160KW; the pipeline length shall be within 150 meters. The length of excavated roads (urban roads and highways) and temporary occupation of green spaces shall be less than 100 meters, and old and big trees shall be avoided. Newly constructed, expanded and rebuilt urban roads used for less than 5 (five) years after delivery and urban roads that are used for less than 3 (three) years after the completion of major repairs shall be excluded. (II) Gas: For newly developed natural gas user projects within the service scope of Beijing Gas Group, the access length shall be less than 100 meters. (III) Heating: For newly developed user projects for regional heating sources of Beijing District Heating Group, the access length shall be less than 100 meters.