1. A construction project fire protection acceptance application form

2. A project completion acceptance report

3. The as-built drawings of relevant fire protection facilities

Process, Time, Mode and Location, Fees.jpg

1. Time

Working days: 09:00-12:00, 13:30-17:00

2. Mode and Location

Offline: Beijing Municipal Government Affairs Service Center: No. 1, South Road, 3rd Ring Road, Fengtai District, Beijing (the southwestern corner of Liuliqiao)

On line: tzxm.beijing.gov.cn

3. Process

(1) Acceptance of application: 5 working days

(2) Examination and decision: 7 working days

(3) Issuance and delivery of certificate: 3 working days

4. Fees

Free of charge

5. Authority in charge

Beijing Municipal Commission of Housing and Urban-Rural Development

Notes.jpg

1. All documents shall be stamped with the official seal of the constructer.

2. For online applications, fill in the information online and upload scanned copies of documents with the official seal. For applications at counters, a copy of each original document is needed.